Project Description

Hypernaked

Hypernaked approached us wanting a new A/C installation for their entire open plan office space.

In order to minimize any disruption to their business, we installed the units out of hours working throughout the night in order to complete the job quickly and efficiently. The system we chose to install was a Daikin two-pipe system, using cassettes for the indoor units. The decision was made to use cassettes for the internal areas, in-keeping with the current look of the lighting and data cabling, which was run on surface tray.

The outdoor unit had to be installed at ground floor level, due to the cost of using a crane and installing it on the roof. We arranged for scaffolding to be erected outside of the building, allowing us to run the pipes and control cables up to the fourth floor.

We completed the installation on schedule and now the staff at Hypernaked have a fully functioning system, keeping them cool in the summer and warm during those long winter months.