Commercial Office Refurbishment

Project Details
24 Cornhill is a 6-floor office block in London. We maintain the whole buildings air conditioning systems. This project on the 2nd floor was to replace the existing Daikin VRV System with a Mitsubishi Heat Recovery System.
- Removal of the 18 no. existing indoor units
- Installation of the new indoor units in approx. the same position
- Re-pipe to the existing pipework
- Reconnect existing 415v 32A power supply with new isolators
- Install two new BC boxes and additional 13A spurs together with steel plates for the installation
- Run new screened control cables between roof and first floor level
- Electrical testing of power supplies and minor works certificate
Outcome:
This project was completed on time and on budget. It was over a two-week period but with the team of 7 engineers working nights to alleviate the disruption to the daytime running of the office.






Contact Us
For more information on how we can help your business